| S.N. | Name of Building | Source of Funding | Stage (Complete) | Stage (Inomplete) |
|---|---|---|---|---|
| 1 | Administrative Building | ICAR | Completion Date : # Plinth area (Sq.m) : # Expenditure (Rs.) : # |
Starting Date : Plinth area (Sq.m) : Status of construction : completed |
| 2 | Farmers Hostel | ICAR | Completion Date : # Plinth area (Sq.m) : # Expenditure (Rs.) : # |
Starting Date : Plinth area (Sq.m) : Status of construction : completed |
| 3 | Staff Quarters (6) | ICAR | Completion Date : # Plinth area (Sq.m) : # Expenditure (Rs.) : # |
Starting Date : Plinth area (Sq.m) : Status of construction : completed |
| 4 | Demonstration Units (2) | ICAR | Completion Date : Plinth area (Sq.m) : Expenditure (Rs.) : |
Starting Date : Plinth area (Sq.m) : Status of construction : |
| 5 | Fencing | ICAR | Completion Date : Plinth area (Sq.m) : Expenditure (Rs.) : |
Starting Date : Plinth area (Sq.m) : Status of construction : |
| 6 | Rain Water Harvesting System | ICAR | Completion Date : Plinth area (Sq.m) : Expenditure (Rs.) : |
Starting Date : Plinth area (Sq.m) : Status of construction : |
| 7 | Threshing Floor | ICAR | Completion Date : Plinth area (Sq.m) : Expenditure (Rs.) : |
Starting Date : Plinth area (Sq.m) : Status of construction : |
| 8 | Farm Godown | ICAR | Completion Date : Plinth area (Sq.m) : Expenditure (Rs.) : |
Starting Date : Plinth area (Sq.m) : Status of construction : Completed |
| 8 | Seed Processing Plant & Storage | ICAR | Completion Date : Plinth area (Sq.m) : Expenditure (Rs.) : |
Starting Date : Plinth area (Sq.m) : Status of construction : Completed |
| Vehicle | Year of Purchase | Cost (Rs.) | Total kms. Run | Present Status |
|---|---|---|---|---|
| Bolero | 2006 | # | # | Working |
| Tractor | # | # | # | # |
| Motor Cycle | 2019 | 71800 | # | Working |
| S.N. | Name of the equipment | Year of purchase | Cost (Rs.) | Present Status |
|---|---|---|---|---|
| 1 | Desktop Computer (Dell)-3 No.s | 2017 | All are Working | |
| 2 | Multifunction Printer (HP)-2 No.s | 2013 & 2017 | # | Both are Working |
| 3 | Laptop Computer (Dell)-2 No.s | 2013 & 2017 | # | Both are Working |
| 4 | LCD Projector | 2017 | # | Working |
| 5 | K-Yan Projector | 2017 | # | Working |
| 6 | Wi-Fi Router | 2018 | # | Working |
| 7 | BSNL Wi-Max | 2018 | # | Working |
| 8 | Camera (Soni) | 2017 | # | Working |
| 9 | Smart LCD TV 49'(Soni) | 2017 | # | Working |
| 10 | Mrida Parikshak (Mini Soil Test Lab) | 2017 | Working | |
| 11 | Ahuja PA Amplifier | 2019 | # | Working |
| 12 | Multifunction Laser Printer (Brother) | 2019 | # | Working |
| 13 | Inkjet Color Printer (Canon) | 2019 | # | Working |
| 14 | Moterized Projector Screen | 2018 | # | Working |